Foundation Drainage Calculator

Outline
Outline entered as
Trench and pipe
Gravel, geotextile and wells

Slope entered as 1% — shown for reference only. This calculator does not size the pipe or slope for actual water discharge; verify against a proper drainage design.

The geotextile wraps the gravel on all four sides — bottom, both sides and top — with its edges overlapping 300 mm on top: 1700 mm of fabric width per metre of trench, before the joint and waste allowance.

Pipe pieces required6
Gravel volume3.98m³
What to buy
  • Drainage pipe6 pcs × 6 mNeeded: 36 m
  • Drainage gravel3.98 m³
  • Geotextile70.38 m²61.20 m² + 15% waste allowance
  • Inspection wells3 pcs

Rounded up to whole pieces and packs. Pack sizes come from your inputs or are typical ones — check with your supplier before buying.

Pipe
Pipe length36 m
Pipe pieces required6
Slope (reference only)1.0 %
Gravel, geotextile and wells
Gravel volume3.98 m³
Geotextile area70.38 m²
Inspection wells3
Excavation
Excavated volume8.64 m³

About this calculator

This calculator turns a building's perimeter into a French (perimeter) drain materials list — pipe length and pieces, the gravel envelope around the pipe, geotextile fabric to wrap it, inspection wells at regular intervals, and the trench's own excavated volume. Enter the outline as a rectangle or as a list of straight runs.

Formula

total length = 2 x (length + width)                     [rectangle]
             = sum of entered run lengths                [list]

pipe pieces = ceil(total length / stock pipe length)
excavated volume = total length x trench width x trench depth

pipe volume = total length x (pi/4) x pipe diameter^2
gravel volume = total length x trench width x (bed thickness + cover thickness) - pipe volume

geotextile wrap width = 2 x trench width + 2 x (bed thickness + cover thickness) + top overlap
geotextile area = total length x wrap width x (1 + joint overlaps and waste %)

inspection wells = floor(total length / well spacing) + 1

Slope is entered and shown in the breakdown but never used in a calculation — this calculator does not size the pipe or slope for actual water discharge.

Worked example

A closed 10 x 8 m rectangular perimeter, 400 mm wide x 600 mm deep trench, a 110 mm pipe in 6 m stock lengths, a 100 mm gravel bed plus a 200 mm gravel cover, geotextile wrapped all round with a 300 mm overlap on top plus 15% for joint overlaps and waste, inspection wells every 15 m.

total length = 2 x (10 + 8) = 36 m
pipe pieces = ceil(36 / 6) = 6
excavated volume = 36 x 0.4 x 0.6 = 8.64 m³
gravel volume = 36 x 0.4 x 0.3 - pipe volume ≈ 4.32 - 0.34 ≈ 3.98 m³
geotextile wrap width = 2x0.4 + 2x0.3 + 0.3 = 1.7 m
geotextile area = 36 x 1.7 x 1.15 = 70.38 m²
inspection wells = floor(36/15) + 1 = 3

FAQ

Why doesn't this calculator size the pipe or check the slope? Sizing a drain for actual water flow needs a hydraulic calculation — catchment area, rainfall intensity, pipe roughness and the site's real fall — which is well outside a quantity take-off. The slope figure you enter is only carried through to the results for your own reference; verify it against a proper drainage design before building.

Why does the gravel volume subtract the pipe's own volume? The gravel fills the trench around the pipe, not through it — the pipe itself takes up space inside that same envelope, so counting the full trench cross-section as gravel would overstate the gravel needed by the pipe's own volume.

How is the geotextile area worked out? As one strip wrapped all the way round the gravel envelope — trench bottom, both sides and the top — with its two edges overlapping on top, so soil cannot wash into the gravel from any side. Installation guides for drainage geotextiles describe exactly this: line the base and sides, fill the gravel, then fold the fabric over the top with an overlap; they give 300 mm as the minimum overlap, which is the default here. The percentage on top covers overlaps where one roll ends and the next begins, corners and cutting waste. It is a simplified model, not a real cutting layout. (Version 1 of this calculator left the top open and so showed about 40% less fabric.)

Which standard does this follow? None is cited. This is plain geometry (pipe/gravel/geotextile/excavation volumes) plus a simple evenly-spaced well count — no standard governs perimeter-drain quantities generally, and hydraulic sizing (which this calculator doesn't attempt) would be the place any such standard would apply.

Assumptions and limits

Gravel bed/cover thickness, the geotextile top overlap and joint allowance, stock pipe length and inspection well spacing are all user inputs with example defaults, not data for a specific drainage system or soil condition. The trench is modelled with vertical sides and no side-slope allowance (unlike the general excavation calculator, which offers one) — add extra excavated volume yourself if the trench needs battered sides. No drawing is produced — the result is a materials/excavation list only.